A group of segments providing details on delivery points and products and related information using one of both scheduling methods. |
|
|
|
|
A group of segments providing details of the individual line items for both methods. |
|
|
|
|
A group of segments specifying the schedule information for the product identified in the LIN segment. With the delivery point driven method this segment group provides the schedule for the identified delivery point and product. With the product driven method this segment group can be used to summarise all schedules provided with the subsequent delivery point information given in segment group 22. |
|
|
|
|
A group of segments specifying quantity related information for actual delivery, reporting or cumulative quantities and forecast quantities as required for the line item under the schedule conditions of the previous SCC segment. |
|
|
|
|
|
Function: |
|
To specify date, and/or time, or period. |
|
|
|
EAN |
* |
|
|
|
|
M |
|
|
|
|
Date or time or period function code qualifier |
|
|
M |
* |
|
General explanations |
2 |
|
= |
Delivery date/time, requested |
61 |
|
= |
Cancel if not delivered by this date |
63 |
|
= |
Delivery date/time, latest |
64 |
|
= |
Delivery date/time, earliest |
67 |
|
= |
Delivery date/time, current schedule |
69 |
|
= |
Delivery date/time, promised for |
157 |
|
= |
Validity start date |
194 |
|
= |
Start date/time |
206 |
|
= |
End date/time |
266 |
|
= |
Validation date |
362 |
|
= |
End availability date |
419 |
|
= |
Forecast period |
|
|
|
Date or time or period value |
|
|
R |
|
|
|
|
Date or time or period format code |
|
|
R |
|
102 |
|
= |
CCYYMMDD |
203 |
|
= |
CCYYMMDDHHMM |
718 |
|
= |
CCYYMMDD-CCYYMMDD |
|
|
Segment Notes: |
|
This segment is used to provide dates and times relating to the quantity and schedule details in the SCC/QTY segments. This segment may indicate date/time ranges, e.g., the start and end date for a delivery pattern, etc.
Example: DTM+67:200201221400:203' |
|